Resources required to complete stage ten
The resources required to conduct the project closure exercise can be calculated fairly accurately assuming that there are no major outstanding problems to be resolved.
| Step | Resource estimate(days) | Description |
| 1 | 5 | Project resource to produce report including completed checklist |
| 2 | 3 | Project resource to complete chapter in report relating to ongoing support agreement |
| TotalSteps 1 - 2 | 8 |