Resources required to complete stage nine
The resources required to measure the results can be calculated fairly accurately. What cannot be predicted with any great accuracy is the scale of the resource that may be required to correct any problems reported back by these reviews.
| Step | Resource estimate (days) | Description |
| 1 | 2 | Project resource to make case for measuring results and high level plan |
| 2 | 10 | Project resource to measure tactical benefits obtained at key milestones in project assuming measure results for two steps in each roll out and two processes in phase six |
| 3 | 10 | Project resource to measure strategic benefits obtained at key milestones in project assuming measure results for two steps in each roll out and two processes in phase six |
| 4 | 5 | Project resource to feed results back into project and adjust plans accordingly |
| TotalSteps1 - 4 | 27 |
Assuming that you cover two steps at step two and three and two processes at step four then in total stage nine should take some 27 days to complete.