University of Bolton, Design Studio Project
| Contact Details: | Mike Lomas, Head of Collaborative Partnerships and Employer Engagement, M.lomas@bolton.ac.uk Andy Smith, Business Development Manager, Design Studio, A.Smith@bolton.ac.uk |
| Type of Project: |
The Project has aspects of both a new build and a refurbishment. The building was originally 8 storeys and the top five floors were removed. The remaining three floors were reconfigured and made into the Design Studio - the inside is now completely different to how it looked originally. This was done as it made economical sense - it was cheaper to reduce and renovate the original building than to knock it down and re-build. |
| Start/End Date: | It has been open since summer 2003 and the project took 18 months to complete. |
Funding Sources
Approximately £1.7m came from European Regional Development Fund (ERDF). Some money from HEFCE poor estates fund and the rest was paid by University of Bolton.
Cost of Project
Project cost £6.3m (this includes cost of demolishing parts of original building).