Loughborough University
| Space: | Open3 |
| Opened: | 2007 |
| Respondent: | Dr Graham Walton |
| Role: | Service Development Manager, Loughborough University Library |
Open3 is a dedicated area of the existing university library; it is managed
by library services and functions as a group-working and social commons.
The library was completed in 1980 and is a 3-storey concrete framed building
with recessed bands of glazing. Essentially it is square in plan with blockwork
cores organised at 45° to the main grid containing services and stairs.
The existing building has no specific issues with heating; lighting or ventilation
and therefore the physical infrastructure of the library remained unaltered
other than providing additional extract over the café servery.
Open3 originally only provided fixed PC workplaces. Wireless was introduced
to the space 6 months after opening and additional perimeter dado power supply
is being installed over Summer 2007 due to the increase in laptop usage. The
university has been tracking laptop use and despite its increase there is still
a continuing requirement for fixed PCs, particularly favoured by students are
those with the provision of adjacent layout space.
Originally the building was laid out as a traditional library with silent
study areas only, however behaviour and noise were becoming issues because
students were using the larger format tables for group working. Library services
came to realise that with the increase in student involvement on collaborative
projects, the zoning of different types of study space would be required in
order to manage the noise issue. Initially group work was confined to zones
within each floor this however created a disturbance to others. Open3
came into being on deciding to bring all group working into level 3, the main
entrance level, providing workplaces for 200 users and reclaiming the adjacent
under-utilised teaching spaces to provide enclosed group working spaces. The
remaining 2 floors still operate as silent study areas for individual work.
Very little of the furniture used in Open3 was purchased new; it was mainly
redeployed from elsewhere therefore the budget for creating Open3 was a minimal £5k.
Separate funding was received for bringing in a franchise to operate a café adjacent
to the library entrance. Initially the café was accessed separately
from the outside but, with the creation of Open3, it has been fully combined
into the group working area, providing a blended version of a social commons.
The policy of permitting drinking and eating, of hot and cold food, throughout
the café and Open3 has proved to be conducive to reinforcing the no
food and drink rule in the levels 1 & 2 and subsequently the need for monitoring
has been reduced. The success of the social commons has led to plans to introduce
additional soft seating areas over Summer 2007.
Access to the building isn't normally 24/7 although there have been 2 trial
periods of 4 and 7 weeks this year. These proved extremely successful producing
an increase in footfall of 20,000 with no greater increase in management issues
other than in relation to cleaning. The impact that Open3 would have on the
scale of the cleaning task was relatively unforeseen at the outset. Now that
it has been identified an increased budget has been allocated and the task
of cleaning is being managed according to the requirements of the intensive
space usage that such a space implies.
There is a policy of no signage in Open3; this has resulted in an area that
is more or less self-policing and requiring minimal management. Open3 is a
good example of a very low cost venture bringing a high return in terms of
usage and positive feedback from users.
This Open Plan Case Study originates from the 2007 JISC-commissioned study into the Design and Management of Technology-Rich Learning and Teaching Spaces in Further and Higher Education in the UK by Les Watson, Hugh Anderson (Principal, haa design) and Katherine Strachan (Architect, haa design).


