Newham College of Further Education, London
| Contact Details: | Philip.Badman@newham.ac.uk Brian.Cooper@newham.ac.uk |
| Type of Project: | Refurbishment to create two 'concept classrooms' on the East Ham and Stratford campuses. The East Ham development centres on three c.50m2 classrooms being converted into one new learning suite. The work at Stratford will begin summer 2007. |
| Start/End Date: | East Ham Campus trial due to open March 2007. Stratford Campus trial site will go into construction over the summer 2007. |
Funding Sources
Entirely self funded from college resources.
Cost of Project
The cost of the East Ham campus project is £150,000 + VAT for the building works, an IT investment of c. £50,000 inclusive, and a furniture budget of £50,000.