Portland College, ILT Learning Centre, Mansfield, Nottingham
| Contact Details: | Clyde Hinton, Dawn Green |
| Type of Project: | New Build. |
| Start/End Date: | First strands of concept 1997 - completed 2006. Work commenced on the site in May 2005 and the building phase was completed in June 2006, at this point the building was handed over to the College by the contractors and the equipping of the centre commenced. |
Funding Sources
The steering committee was established to spearhead the National Appeal. The committee worked tirelessly to raise huge amounts of money from a variety of sources and by July 2006 the National Appeal had reached a total of £3.2 million for capital costs and £370,000 for equipment and technology.
A small number of College governors formed a working party to monitor all aspects of the project. The group met on a regular basis to assess and modify design plans and project implementation and manage the budget. The working party also planned and implemented the tendering process for the main contractor.